Phase 1 of the Healthy Route was installed in January 2021, initially as a temporary scheme, which consisted of:
Four new zebra crossings
A new two-way cycle track protected with traffic wands
A banned left turn for general traffic from Rosendale Road into Turney Road
Phase 1a is being installed in spring 2024.
As part of making this section of the route permanent, the following improvements are proposed to the existing scheme:
Phasing and timings of the works:
Due to safety considerations, road closures will be necessary at the following locations, with access available for residents only:
Phase Plan Reference | Date* |
| Location | ||
---|---|---|---|---|---|
Phase 7 | 4 Mar – 31 Mar 2024 | 4 weeks | Guernsey Grove Junction with Rosendale Road to Croxted Road | ||
Phase 8 | 18 Mar - 8 Apr 2024 | 4 weeks | Hawarden Grove Junction with Rosendale Road to Croxted Road |
*Due to the nature of the site, dates may be subject to change
Important things to note
During resurfacing, no vehicles can be parked in the resurfacing area. Please relocate your vehicles to a nearby road prior to resurfacing work commencing. Vehicles that are not moved will have to be relocated (details on how to find a relocated vehicle are below).
During the work phases the road will be closed. This means there will be no vehicular access within or across the area and no parking while works are being carried out for safety reasons. However, there will be intermittent access for residents during the works, and residents will have full access after-hours (18:00 onwards). During the day when construction is ongoing, access will be limited, depending on which section is being constructed.
Temporary Traffic Orders will be in place to support the ‘No Parking’ cones and signage. Vehicles parked in the coned areas run the risk of receiving a Penalty Charge Notice and possible relocation.
If your vehicle is relocated, please contact Towed Vehicle Tracing Service (TRACE) customer services helpdesk on 0300 077 0100. Vehicles will be allowed back onto the road once the work is complete and where the cones and warning signs have been removed.
If you have any special requirements or need to arrange access for people with disabilities, please contact us on the email address provided below.
Contact Us
We are committed to delivering an efficient, safe project and to keeping the local community informed throughout. Our teams are always happy to answer questions about our work.
For questions relating to the Healthy Route Programme/Strategy, please contact healthyroutes@lambeth.gov.uk
For questions on the Controlled Parking Zone (CPZ), please contact cpzconsultation@lambeth.gov.uk
For questions on Traffic management and phasing, please contact Ringway 0845 646 0059 Lambeth.schemes@ringway.co.uk